Construction Update from Francine Perkins

Montpelier Paving Update —  Two-Week Look Ahead

June 14 — For the remainder of  June, crews will focus on completing the manhole and drainage structure adjustment and crosswalk ramp replacements on State and Main Street as preparation for the final course of paving. As a reminder, in order for final paving of the July 3rd parade route to occur, all manhole and drainage structures need to be adjusted and crosswalk ramps need to be replaced and upgraded.

Final paving of the July 3rd parade route on Main and State Street is estimated to start the week of June 26, weather permitting.

The remainder of the sidewalk replacement work that is not required to be completed before final paving will continue into July.

Other Construction Updates:

Project Location:   VT 12-Northfield Street — new water, sewer, storm water improvements, sidewalks and a stabilized road base.

Northfield Street Detour Routes — Effective Thursday, June 8 — Due to unexpected traffic impacts on the Northfield Street project, the following detour will remain in effect through October 2017: 1) Dog River Road is marked as a truck detour route. 2) Derby Drive is signed as detour route. 3) Alternating one-way local traffic will be maintained within the Northfield Street construction zone including any work on Memorial Drive.

Memorial Drive/Northfield Street Intersection Night Work — Water and sewer infrastructure upgrades in the Memorial Drive/Northfield Street Intersection have been rescheduled to occur at night. The work is scheduled for Wednesday night (June 14) through Friday night (June 16).

Main Street – Structure Adjustment: 1) School Street to the Roundabout — Work Hours (5 p.m. – midnight) — Crews are planning to work on adjusting existing manhole and drainage structures between School Street and the Roundabout.  Typical equipment used for this work are saws and jackhammers. 2) State Street to School Street — Night Work (7 p.m. to 7 a.m.) — Crews will continue adjusting structures.

Sidewalks– (Work Hours – 7 p.m. to 11 a.m.) Crews will replace and upgrade sidewalk ramps at various crosswalks along Main Street to School Street, including at State and Main Street.

Sidewalk preparation work will be done overnight and the new concrete will be poured between 7 a.m. and 11 a.m.  Street parking will be blocked off  and will be re-opened when work is completed.

Night work (7 p.m. to 11 a.m.) — Crews will be replacing and upgrading the sidewalk ramps at all crosswalks on State Street between the Post Office and Main Street. Preparation work will be done overnight and the new concrete will be poured between 7 a.m. 11 a.m.

Street parking will be blocked off in active work areas and will be re-opened when work is completed.

It is illegal to use any handheld portable electronic devices while driving. The law carries fines of up to $200 with points assessed if the violation occurs in a work zone.

Contact Francine Perkins, Project Outreach Coordinator, FRP Enterprises, LLC with any questions or concerns with regards to the project at 479-6994.